Why This Chapter Exists

Application rollback is easy only when database state is compatible. Most production rollback failures happen at the boundary between application version and schema version.

This chapter defines a safe migration discipline:

  • backward-compatible schema first
  • application rollout second
  • destructive schema changes last
  • explicit rollback windows and feature flag gates

Learning Objectives

By the end of this chapter, learners can:

  • explain expand/contract migration strategy
  • design rollback-safe deploy sequence for app + schema
  • execute a migration incident drill with evidence capture
  • define break-glass rules for failed migrations

Current Project State

  • backend service currently does not depend on production DB reads/writes for core flow
  • chapter uses migration workflow simulation on CNPG/PostgreSQL targets
  • when backend login + DB flow is added, this chapter becomes mandatory release gate

The Incident Hook

A release includes application code and schema migration in one step. Migration drops/renames a column used by previous app version. New deployment fails health checks; rollback of application image succeeds, but old app cannot read data anymore. Incident duration expands because “app rollback” alone cannot recover service.

What AI Would Propose (Brave Junior)

  • “Apply migration and deploy together in one PR.”
  • “If deploy fails, just rollback image tag.”
  • “Skip feature flags to reduce complexity.”

Why this sounds reasonable:

  • fewer moving parts in one release
  • fast visible progress

Why This Is Dangerous

  • schema and application coupling creates irreversible rollback paths
  • destructive changes remove safety window
  • partial rollout can leave mixed-version traffic against incompatible schema

Guardrails That Stop It

  • expand/contract strategy only
  • migration scripts must be idempotent and reviewed
  • app rollout uses feature flags for behavior gating
  • rollback plan includes data compatibility checks
  • destructive DDL only after verification window and explicit approval

Repository Mapping

  • data platform baseline: flux/infrastructure/data/cnpg-clusters/
  • backup/restore baseline: docs/course/chapter-10-backup-restore/
  • promotion baseline: docs/course/chapter-04-gitops/

Safe Workflow (Step-by-Step)

  1. Create expand migration (additive only).
  2. Deploy migration job and verify schema compatibility.
  3. Deploy app with new code path behind feature flag (flag off).
  4. Enable flag gradually and monitor SLO/error budget.
  5. Keep rollback window open until confidence threshold.
  6. Run contract migration only after explicit approval.

Lab Files

  • lab.md
  • runbook-rollback-migrations.md
  • quiz.md

Done When

  • learner can run migration drill with rollback-safe sequence
  • learner can distinguish app rollback vs data rollback limits
  • learner can define no-go conditions before destructive migration

Lab: Rollback-Safe Migration Drill (Advanced)

Lab: Rollback-Safe Migration Drill (Advanced)

Goal

Run a controlled migration rollout in non-production with explicit rollback points:

  • apply additive schema migration
  • deploy app-compatible change behind feature flag (simulated)
  • validate rollback path
  • define contract migration go/no-go decision

Prerequisites

  • access to develop namespace
  • CNPG cluster available (or any PostgreSQL test target)
  • backup/restore workflow familiarity from Chapter 10

Current-state note:

  • if backend DB login flow is not implemented yet, run this as schema/process simulation
  • keep the same sequence; replace simulated step with real app checks later

Quick checks:

Quiz: Chapter 16 (Rollback and Data Migrations)

Quiz: Chapter 16 (Rollback and Data Migrations)

Questions

  1. Why is “application rollback” not always enough after a bad migration?

  2. What is the correct high-level order in expand/contract strategy?

  3. Which type of migration is safe to run before new application code?

  4. Why should destructive migrations be delayed?

  5. Which statement is correct?

  • A) Drop-column migration can run before compatibility verification.
  • B) Feature flags reduce rollback risk during migration rollout.
  • C) Migration rollback should always drop newly added columns immediately.
  1. Name two mandatory preconditions before contract migration.

    Runbook: Rollback and Migration Operations (Advanced)

    Runbook: Rollback and Migration Operations (Advanced)

    Purpose

    Operate application + schema releases with explicit rollback safety and minimal blast radius.

    Scope

    This runbook covers:

    • migration classification and sequencing
    • rollback execution order
    • incident handling for migration-related failures
    • destructive migration approval gates

    Migration Types

    1. Expand (safe/additive):
    • add nullable columns
    • add new tables/indexes
    • keep old schema path valid
    1. Contract (destructive):
    • drop/rename columns
    • remove legacy constraints/paths
    • only after stable compatibility window

    Pre-Deploy Checklist

    1. Migration classified (expand or contract).
    2. Rollback window defined with owner and duration.
    3. Backup/restore evidence is fresh.
    4. Feature flag plan exists for new code path.
    5. Monitoring and alert thresholds are confirmed.

    Rollout Sequence (Mandatory)

    1. Expand migration.
    2. Application deploy with flag OFF.
    3. Controlled flag enable.
    4. Observe stability window.
    5. Contract migration (approval required).

    Rollback Order

    If incident occurs after expand + app deploy: